Do you need building consent?

Most substantial building work needs consent, but some low-risk work is exempt. The important point is that exempt does not mean unregulated.

The short answer

New homes, additions and structural alterations generally need a building consent. Some lower-risk work can be exempt under the Building Act, but the exact conditions matter. Your local building consent authority, usually your council, is the right place to confirm a marginal or project-specific case.

All building work must comply with the New Zealand Building Code, even when it does not need a building consent.

An exemption changes the consent requirement. It does not remove the owner's responsibility for compliant work.

Work that commonly needs consent

MBIE's current homeowner guidance says consent is commonly required for work including:

  • new buildings, additions and structural alterations
  • some demolition, re-piling and earthworks
  • plumbing or drainage that creates an additional sanitary fixture
  • decks, platforms or bridges more than 1.5 metres above ground
  • retaining walls above the relevant exemption limits
  • larger sheds, pools and associated pool barriers

This is a starting list, not a project decision. Work that appears similar can fall on different sides of an exemption because of its dimensions, location, structural effect or who carries it out.

What exempt work still requires

Schedule 1 exemptions cover defined categories of lower-risk work. Some can be carried out by anyone; others require a Licensed Building Practitioner, Chartered Professional Engineer or another authorised professional. In every case, the work must still meet the Building Code and other applicable law.

Before treating work as exempt, check the full conditions, not just the project label. A deck, retaining wall, shed or alteration may be exempt at one scale and need consent at another.

Granny flats: the 70 square metre exemption

Since 15 January 2026, Schedule 1A of the Building Act lets a homeowner build a new, single-storey, standalone, self-contained dwelling of up to 70 square metres without a building consent. It is the largest exemption in the Act and it works differently from the Schedule 1 list above.

  • The dwelling must be new, at least 2 metres from boundaries and other residential buildings, built in light timber or steel framing or a certified composite product, with lightweight roof and wall cladding, its own power supply, no solid fuel heater and no level-entry shower.
  • Licensed Building Practitioners must design and carry out or supervise the restricted building work and issue Certificates and Records of Work.
  • The owner must get a project information memorandum from the council before work starts, finish within two years, and lodge the plans and records with the council within 20 working days of completion. The council files them but does not inspect and does not issue a code compliance certificate.
  • Resource consent rules apply separately under the national standard for detached minor residential units and the district plan.

MBIE revised its Granny Flats Exemption Guidance on 8 October 2026 (version 2). Bracen's granny flat rules guide walks through the conditions, the process and the penalties in plain language, and the granny flat cost guide compares the exempt and consented budgets.

A practical decision path

  1. Define the work. Record dimensions, location, structural changes, plumbing or drainage changes and the intended use.
  2. Check the official guidance. Use MBIE's consent checker and exemption guidance for the current conditions.
  3. Check other approvals. Resource consent, district-plan rules or other permits can still apply even if building consent is not required.
  4. Confirm anything marginal. Ask the council or an appropriately qualified professional before physical work begins.
  5. Keep the evidence. Retain plans, product information, professional advice, invoices and records of the completed work.

Building consent is not the end of the process

If consent is required, the approved plans and specifications become the basis for the work and inspections. Changes during construction may need to be recorded as a minor variation or handled through a formal amendment. At completion, the owner applies for a code compliance certificate so the council can assess whether the consented work was completed in accordance with the consent.